Greencroft Comprehensive School, Annfield Plain

Asbestos Removal / Demolition works to vacant school buildings, Total area 2700m2 Highest buildings were at 10 metres. 

  • Client: Robertson Construction England, Level 4 West Tower, Baltic Place, South Shore Road, Gateshead, NE8 3AE

  • Value: £215,000.00 Plus V.A.T

  • Duration: 12 Weeks (November 2014 to February 2015)